Structural Steel Inspection in Center City, PA

Structural steel inspection is the special inspection required by Philadelphia Building Code Table 1705.2 when your project uses steel beams, columns, or structural frames. Most Fishtown renovation projects remove load-bearing walls to create open floor plans by installing steel I-beams to support the second floor. Most Front Street new construction uses structural steel frames with steel beams and columns supporting concrete slabs in 4-6 story mixed-use buildings. Table 1705.2 distinguishes between continuous inspection where the engineer is on-site during the entire operation (required for welded moment connections and high-strength bolted connections) and periodic inspection with scheduled visits (allowed for standard bolted connections and simple welds). Your contractor orders steel from a fabricator, steel is delivered to site, a crane lifts beams into place, connections are bolted or welded, and the engineer inspects at multiple stages. Typical steel projects require 2-4 inspections for small residential beam installations to 12-24+ inspections for large multi-story steel frame buildings.

Make Safe Permits

Certified Civil Engineer

Fully Licensed & Insured

Certified Structural Engineer

What to Expect With Structural Steel Inspection
  • Coordination with steel erection schedule is critical. Fishtown steel installations typically happen 6am-10am to avoid traffic congestion in narrow streets before Market-Frankford El rush hour. Crane rental costs $2,000-$5,000 per day and contractor wants beam set in 4-8 hours for one day rental. If we find problems during erection that delay placement, the crane sits idle at $250-400 per hour.
  • Each inspection typically takes 1-3 hours on-site. Simple beam installation equals 1-2 hours. Complex welded moment connection equals 2-3 hours for weld inspection alone. We inspect mill certificates before steel leaves the ground, verify beam placement during crane operations, and check connections after bolting or welding is complete.
  • Coordination with steel erection schedule is critical. Crane rental costs $2,000-$5,000 per day and contractor wants beam set in 4-8 hours for one day rental. If we find problems during erection that delay placement the crane sits idle at $250-400 per hour.
Structural Steel Inspection
Why Structural Steel Inspection Matters
  • Table 1705.2 requires special inspection of structural steel with different requirements for different connection types. Continuous inspection is required for welded moment-resisting connections, high-strength bolted connections where design assumes full pretension, and any structural welding per AWS D1.1 where specified. Periodic inspection is allowed for standard bolted connections, simple shear connections, and floor or roof deck welding. If your structural engineer designed a moment connection or slip-critical bolted connection, we must be on-site during the entire welding or bolting operation. L&I will not issue Certificate of Occupancy if continuous inspection was required but only periodic inspection was performed.
  • Steel connection failure causes catastrophic collapse. Steel beams support enormous loads with a typical Fishtown townhouse W10x22 beam supporting second floor carrying 15,000-25,000 pounds total load. If connections fail because of inadequate welds that crack under load or under-torqued bolts that slip, the beam drops. Result is second floor collapses into first floor with people, furniture, and equipment falling 10-12 feet, occupants killed or catastrophically injured, and neighboring buildings damaged if collapse affects party walls.
  • Steel fabrication errors are expensive to fix after erection. We inspect steel at delivery before the crane lifts it. We verify beam length measured with tape compared to drawings, flange width and web depth to verify correct size, bolt holes drilled at correct spacing if pre-drilled, and mill certificates provided to prove steel grade. If steel is wrong because fabricator built wrong size, we stop the erection before crane lifts it. Contractor returns steel to fabricator who builds correct beam taking 2-4 weeks additional lead time and contractor reschedules crane.
Why Structural Steel Inspection Matters
How StrucTech Handles Structural Steel Inspection
  • We inspect mill certificates before steel leaves the ground. Mill certificates prove steel grade typically A992 Grade 50 for structural beams. Each beam has stenciled marking showing size, heat number for traceability to steel mill, and grade. We verify mill certificate heat numbers match beam stenciling. We measure critical dimensions including beam length compared to structural drawings and flange width. We photograph beam markings and measurements. If mill certificates are missing or don't match steel delivered, we reject the steel before crane touches it.
  • We've completed 100+ structural steel inspections in Fishtown and know common beam sizes for rowhouse renovations including W8x15 for short spans, W10x22 for medium spans at typical rowhouse width, and W12x26 for longer spans or heavy loads supporting three stories above. We know typical connection details including simple shear connections, moment connections, and bearing plates. We verify during erection that beam is level, beam bearing is full contact with no gaps, and beam alignment matches structural drawings.
  • We use calibrated inspection tools including fillet weld gauge that measures weld leg size, torque wrench calibrated annually that verifies high-strength bolt torque, magnetic particle inspection kit for critical welds detecting surface cracks invisible to naked eye, and visual weld inspection looking for defects like cracks, porosity as tiny holes in weld, undercut as groove melted into base metal, and overlap where weld doesn't fuse properly. We document deficient welds with photos showing defect with measuring scale, contractor's welder repairs defects by grinding out and re-welding, and we re-inspect repairs.
How StrucTech Handles Structural Steel Inspection
Common Questions About Structural Steel Inspection
How long does structural steel inspection take in Fishtown?
1-3 hours per inspection depending on complexity and number of pieces. Pre-erection inspection at steel delivery equals 1-2 hours for small projects or 2-4 hours for larger projects. Erection inspection on-site during crane operations equals 1-2 hours for single beam placement or 4-8 hours for multiple beams erected same day. Welding inspection continuous for moment connections equals 2-6 hours depending on number of welds. Bolting inspection periodic for standard connections equals 1-2 hours checking random bolts with torque wrench.
What's the difference between continuous and periodic inspection?
Continuous inspection means we're on-site during the entire operation watching welder complete every weld pass or ironworker torque every bolt. Required by Table 1705.2 for welded moment-resisting connections, high-strength bolted connections where design assumes full pretension, and structural welding per AWS D1.1 where specified. Periodic inspection means we visit at scheduled intervals after bolting is complete or after welding is complete to inspect the finished work. Allowed for standard bolted connections, simple shear connections, and floor or roof deck welding. Your structural engineer determines which type is required.
Can you inspect after steel is already erected and connected?
Partially. We can inspect bolt presence verifying bolts are installed in all holes, weld existence verifying welds are present where shown on drawings, and general alignment verifying beam is level and bearing appears adequate. We cannot verify bolt torque since once bolts are tightened we cannot verify pretension was achieved without destructive testing, weld quality inside the weld since cracks and porosity are internal only visible during welding or with expensive ultrasonic testing, or bearing contact since once beam is loaded we cannot verify full contact without removing load.
Yes for erection inspection. We verify rigging with crane slings attached properly to beam and lifting points correct, lift path with no overhead obstructions and adequate clearance from Market-Frankford El on Front Street, and placement with beam lowered into position and bearing surface checked for full contact. Crane operator won't lift until we approve rigging. We're on-site during the lift not before or after. Fishtown steel erections typically happen 6am-10am before traffic congestion.
Yes for erection inspection. We verify rigging with crane slings attached properly to beam and lifting points correct, lift path with no overhead obstructions and adequate clearance from Market-Frankford El on Front Street, and placement with beam lowered into position and bearing surface checked for full contact. Crane operator won't lift until we approve rigging. We're on-site during the lift not before or after. Fishtown steel erections typically happen 6am-10am before traffic congestion.
AWS D1.1 Structural Welding Code requires welders to be certified for the specific welding processes and positions used. Common certifications are SMAW stick welding, FCAW wire-feed welding, and GMAW MIG welding in flat, horizontal, vertical, and overhead positions. Welder must have current certification card since certifications expire after 6 months of non-use or when welder changes employers. We verify welder certification before welding begins by inspecting certification card and photographing for documentation. If welder is not certified, we stop the work.
AWS D1.1 Structural Welding Code requires welders to be certified for the specific welding processes and positions used. Common certifications are SMAW stick welding, FCAW wire-feed welding, and GMAW MIG welding in flat, horizontal, vertical, and overhead positions. Welder must have current certification card since certifications expire after 6 months of non-use or when welder changes employers. We verify welder certification before welding begins by inspecting certification card and photographing for documentation. If welder is not certified, we stop the work.

Our Simple Step by Step Process

Reliable Structural Engineering & Inspection Services handled start to finish.

DISCOVER WHAT Center City, PA CUSTOMERS HAVE TO SAY ABOUT StrucTech

OUR REVIEWS

REVIEW US

ON GOOGLE

Where We Provide

Structural Steel Inspection

  • Center City, PA

  • Northern Liberties, PA

  • University City, PA

  • Main Line, PA

  • Graduate Hospital & Point Breeze, PA

  • South Philadelphia, PA

  • Center City, PA

  • Old City & Society Hill, PA

  • Manayunk & Roxborough, PA

  • Kensington & Port Richmond, PA

Other Services We Provide

Need something else? Check out the

other services we offer for Structural Engineering & Inspection Services.

What We Can Help You With.

Our Services

Special inspections

Special inspections are when a licensed structural engineer monitors your construction project to verify the work matches approved drawings and meets code requirements. Philadelphia requires this for any project using structural steel beams, concrete slabs, high-strength bolts, or structural welding. The inspector visits your site at critical stages during construction, documents what the contractor built, catches problems before they're covered up, and provides certification to L&I when the work is done. Without this certification, L&I won't issue your Certificate of Occupancy and you can't sell or rent the building. Most Fishtown projects over two stories need special inspections, and your architect lists exactly which inspections are required when they submit your permit application.

Learn More →
Underpinning Inspection

An Underpinning inspection is when a structural engineer monitors excavation work next to existing buildings to make sure neighboring properties don't collapse or settle. Philadelphia requires this whenever you dig deeper than 5 feet within 10 feet of an adjacent structure, which is basically every basement excavation in Fishtown's narrow rowhouse lots. Your contractor digs in small sections, pours concrete to support the neighbor's foundation in each section, then moves to the next section. This process repeats 16-24 times for a typical rowhouse. The engineer must be on-site during excavation and concrete placement for every single section to verify the work protects adjacent buildings. Without this documentation, L&I won't issue your Certificate of Occupancy, and if your neighbor's building settles or collapses, you're liable for all damages.

Learn More →
Foundation Inspections

A Foundation inspection is when a structural engineer assesses your building's foundation to identify problems and estimate repair costs. You need this before buying a property to know what you're getting into, before planning a renovation so your architect knows what they're working with, or when you've discovered problems like cracks in walls, doors sticking, floors sloping, or water coming through the basement. Most Fishtown rowhouses are 100-150 years old with stone or brick foundations from the 1800s-1950s. These foundations were fine when built but often show deterioration now from lime mortar crumbling, stones separating, freeze-thaw damage, or settlement from inadequate footings. The engineer accesses your basement and crawlspace, measures cracks, tests mortar condition, checks for water infiltration, documents settlement, and assesses whether the foundation is structurally adequate. You get an 8-15 page report with photos, detailed findings, and repair recommendations with cost estimates.

Learn More →
Make Safe Permits

Make safe permits are emergency L&I permits required when a building partially collapses, shows imminent collapse signs, or gets red-tagged as unsafe. When L&I red-tags a building under Section 110, you must obtain a make safe permit to perform emergency stabilization work like installing shoring, bracing walls, removing dangerous elements, or partial demolition. This permit requires a Pennsylvania-licensed structural engineer to design the emergency work, provide stamped drawings, supervise the stabilization, and certify completion to L&I. The make safe permit is processed on an emergency basis, typically issued within 24-48 hours rather than the normal 2-4 week permit review. Philadelphia averages 300 building collapses per year, many in Fishtown from adjacent excavation damage, roof overloading, fire damage, or century-old buildings deteriorating. Most make safe permit applications happen between 11pm and 3am when buildings collapse during construction, storms, or snow loading events.

Learn More →
Emergency Structural Engineering

Emergency structural engineering is the immediate response when your contractor discovers structural failure during renovation, a load-bearing element fails unexpectedly, or you need same-day structural assessment to keep your project moving. This is when you call us directly because your contractor removed what they thought was a non-load-bearing wall and the second floor sagged 2 inches, opened a wall and found severe termite damage, discovered the existing beam is undersized for the addition you're building, or noticed floor joists rotting where they meet the foundation. In Fishtown's 1800s-1950s rowhouses, contractors frequently discover hidden structural problems during demolition because previous homeowners covered problems with drywall rather than fixing them. The engineer responds within 2-4 hours, assesses damage on-site, designs temporary stabilization for the same day so your contractor can continue working tomorrow, and provides permanent repair drawings within 3-7 days so your project stays on schedule.

Learn More →
Slab Inspection

Mat slab inspection is the code-required inspection by a structural engineer before your contractor pours the foundation slab for new construction or basement excavation projects. Philadelphia Building Code Table 1705.3 requires special inspection of concrete reinforcement placement for most projects, with limited exceptions for simple 1-2 story buildings. Most Fishtown new construction like 3-4 story townhouses and Front Street mixed-use buildings require mat slab inspection. Your contractor excavates to foundation depth, installs vapor barrier and compacted stone base, places reinforcing steel in a rebar grid, and calls the engineer for inspection. The engineer arrives before concrete trucks (typically 6:30am for 7am pour), inspects rebar size, spacing, and cover distances, verifies excavation depth and preparation, approves or identifies corrections, and documents with photos. The contractor proceeds with concrete pour only after engineer approval, and the engineer submits a report to L&I for the permit file.

Learn More →
Concrete & Rebar Inspection

Concrete and rebar inspection is the special inspection required by Philadelphia Building Code Table 1705.3 for elevated slabs, concrete columns, concrete walls, beams, and any structural concrete element beyond simple ground-level foundations. Most Fishtown new construction projects require multiple concrete inspections throughout construction as each floor or structural element is formed and poured. This is different from mat slab inspection which is a one-time inspection before foundation pour. Concrete and rebar inspection happens repeatedly during construction as each floor slab, column, or wall is built. Your contractor builds formwork (temporary wooden forms that hold wet concrete), installs reinforcing steel per structural drawings, calls the engineer for inspection before pouring, and the engineer approves so concrete can be placed. This repeats for each floor slab, each column, and each wall that contains structural concrete, typically requiring 3-8 inspections for a 3-story Fishtown townhouse or 12-24+ inspections for larger buildings.

Learn More →
Structural Steel Inspection

Structural steel inspection is the special inspection required by Philadelphia Building Code Table 1705.2 when your project uses steel beams, columns, or structural frames. Most Fishtown renovation projects remove load-bearing walls to create open floor plans by installing steel I-beams to support the second floor. Most Front Street new construction uses structural steel frames with steel beams and columns supporting concrete slabs in 4-6 story mixed-use buildings. Table 1705.2 distinguishes between continuous inspection where the engineer is on-site during the entire operation (required for welded moment connections and high-strength bolted connections) and periodic inspection with scheduled visits (allowed for standard bolted connections and simple welds). Your contractor orders steel from a fabricator, steel is delivered to site, a crane lifts beams into place, connections are bolted or welded, and the engineer inspects at multiple stages. Typical steel projects require 2-4 inspections for small residential beam installations to 12-24+ inspections for large multi-story steel frame buildings.

Learn More →
Facade Inspection (5-Year)

Facade inspection is the code-required inspection every 5 years for buildings over 3 stories or 40 feet tall per Philadelphia Code Chapter 14-1600. This applies to many Fishtown buildings including converted mills that are 4-6 stories, Front Street mixed-use developments that are 4-8 stories, and some taller rowhouses with pilot-house construction pushing height over 40 feet. A Pennsylvania-licensed Professional Engineer or Registered Architect must inspect the entire building exterior including walls, parapets, cornices, balconies, fire escapes, signs, and awnings looking for deterioration, loose elements, cracks, spalling where concrete or brick breaks off, and any conditions that could cause falling debris. The inspection requires close-up access using aerial lift, scaffolding, or rope access for tall buildings, photo documentation of all defects, and a stamped report submitted to L&I certifying the building is safe or identifying required repairs. Buildings overdue for inspection receive L&I violations with accumulating fines until inspection is complete.

Learn More →
Excavation Shoring Inspection

Excavation shoring inspection is the code-required monitoring by a structural engineer when your contractor digs deeper than 5 feet and uses temporary support systems called shoring to prevent cave-ins. OSHA and Philadelphia Building Code require shoring for excavations over 5 feet deep or when excavating near existing structures to prevent soil from collapsing into the excavation, protect workers from being buried alive, and prevent adjacent buildings from settling. Most Fishtown basement excavations that lower basement floors to add ceiling height or dig new basements under existing buildings require shoring because you're digging 8-12 feet deep and working within inches of adjacent rowhouse foundations. Typical shoring systems are steel sheet piling with interlocking steel sheets driven into ground, soldier piles and lagging with vertical steel beams and horizontal wood planks, or trench boxes as steel cages protecting workers inside excavation. Your contractor installs shoring, the engineer inspects before excavation proceeds, the engineer monitors during excavation, and the engineer certifies shoring performed adequately.

Learn More →
Structural Load Analysis

Structural load analysis is the engineering calculation required when you're adding loads to an existing building or when your architect needs to verify existing structure can support proposed changes. Most Fishtown renovation projects involve structural modifications like removing walls between living room and kitchen to create open floor plan requiring beam to carry second floor load, adding third-floor addition or pilot house where existing structure must support additional story, converting rowhouse to multi-unit rental with heavier occupancy loads, or building rooftop deck where existing roof structure designed for snow only not people and furniture and planters. The engineer calculates existing structural capacity, calculates new loads being added, determines if existing structure is adequate, and designs strengthening if needed with new beams, columns, or foundation upgrades. Deliverables are stamped structural drawings showing required modifications and calculations for L&I permit review. This service is separate from inspection services which verify contractor builds what's on the drawings.

Learn More →
Building Structural Assessment

Building structural assessment is the comprehensive evaluation of your entire building's structural system before major renovations, after discovering problems, for property purchase due diligence, or when converting building use. Most Fishtown building assessments happen when developers buy older rowhouses sight-unseen at auction needing to know actual repair costs before committing capital, architects discover hidden damage during design phase like opened walls and found termite damage or rotted framing or previous unpermitted modifications, or property owners plan gut renovations wanting to know what structural surprises await before setting budgets. The engineer inspects foundation to roof including basement walls and floor framing and load-bearing walls and roof structure, identifies all structural deficiencies, categorizes by severity, and provides repair recommendations with cost estimates. This is different from foundation inspection which focuses only on foundation or pre-purchase home inspection which is general not structural-specific. Building structural assessment is engineering-level detailed inspection with stamped report typically 30-80 pages.

Learn More →

Not sure what you need?

Call us at +1 267-310-1172 and we'll help you figure it out.

Ready to Move Forward?

If you need Structural Steel Inspection

or unsure and have questions let's talk.

We'll answer your questions, provide a clear estimate, and schedule a time that works for you.

Unable to find form