Concrete & Rebar Inspection in Center City, PA

Concrete and rebar inspection is the special inspection required by Philadelphia Building Code Table 1705.3 for elevated slabs, concrete columns, concrete walls, beams, and any structural concrete element beyond simple ground-level foundations. Most Fishtown new construction projects require multiple concrete inspections throughout construction as each floor or structural element is formed and poured. This is different from mat slab inspection which is a one-time inspection before foundation pour. Concrete and rebar inspection happens repeatedly during construction as each floor slab, column, or wall is built. Your contractor builds formwork (temporary wooden forms that hold wet concrete), installs reinforcing steel per structural drawings, calls the engineer for inspection before pouring, and the engineer approves so concrete can be placed. This repeats for each floor slab, each column, and each wall that contains structural concrete, typically requiring 3-8 inspections for a 3-story Fishtown townhouse or 12-24+ inspections for larger buildings.

Make Safe Permits

Certified Civil Engineer

Fully Licensed & Insured

Certified Structural Engineer

What to Expect With Concrete & Rebar Inspection
  • Timeline is multiple inspections matching your construction schedule over 3-12 months. Single-family addition with one elevated slab equals 1-2 inspections over 1-2 months, Fishtown 3-story townhouse equals 3-6 inspections over 4-8 months, and Front Street multi-story building equals 8-24 inspections over 6-12 months. Each inspection scheduled 48-72 hours before the pour, arriving 30-45 minutes before concrete trucks.
  • Timeline: Multiple inspections over 3-12 months depending on project size. Small project (single-family addition with one elevated slab) equals 1-2 inspections over 1-2 months. Medium project (Fishtown 3-story townhouse with concrete second floor and roof deck) equals 3-6 inspections over 4-8 months. Large project (Front Street 4-6 story mixed-use with multiple concrete floors) equals 8-24 inspections over 6-12 months. Each inspection is scheduled 48-72 hours before pour, and we arrive 30-45 minutes before concrete trucks at typically 6:15am-6:30am for 7am pour.
  • Each inspection takes 1.5-3 hours depending on complexity. Elevated slab inspection includes verifying formwork plus rebar. Concrete column inspection includes verifying rebar cage and ties. Concrete wall inspection includes verifying horizontal and vertical rebar plus form ties. Each element gets inspected before concrete pour to verify it matches approved drawings.
Concrete & Rebar Inspection
Why Concrete & Rebar Inspection Matters
  • Formwork collapse kills construction workers. Wet concrete weighs 150 pounds per cubic foot. A 20 foot by 30 foot elevated slab that's 6 inches thick equals 300 cubic feet which equals 45,000 pounds or 22.5 tons of wet concrete. This load bears on temporary formwork made of wooden beams and shoring posts. If formwork is inadequate because posts are spaced too far apart, posts bear on loose soil instead of solid base, or bracing is missing, the formwork collapses under load. Workers placing concrete fall 10-15 feet with wet concrete and formwork falling on top of them resulting in deaths or catastrophic injuries. OSHA investigates, the project shuts down for weeks, criminal charges if negligence is found, and lawsuits in the millions.
  • Table 1705.3 requires periodic special inspection of concrete reinforcement. Your structural engineer designed each concrete element with specific rebar sizes and spacing. If your contractor installs wrong sizes or spacing, structural capacity is reduced. Common contractor errors include forgetting the bottom rebar layer in elevated slabs so the slab has only top rebar and is 50% weaker than designed, column ties spaced 24 inches instead of 12 inches so the column will buckle under load, or wall rebar on wrong side. These errors aren't visible after concrete cures, resulting in slabs that crack under live load, columns that crack during earthquake or high wind, and walls that crack under lateral soil pressure.
  • L&I requires continuous documentation throughout construction. When your project is complete and L&I reviews for Certificate of Occupancy, they check the permit file for special inspection reports showing progression through the building with foundation inspected on one date, second floor inspected on another date, third floor inspected on another date, and roof inspected on another date. If inspections are missing or out of sequence, L&I red-tags the project. But concrete is already poured and covered from months ago. You can't inspect rebar buried in cured concrete. Your options are expensive non-destructive testing, core samples, or breaking out sections, and all delay Certificate of Occupancy by weeks.
Why Concrete & Rebar Inspection Matters
How StrucTech Handles Concrete & Rebar Inspection
  • We inspect formwork before rebar is placed which many inspectors skip. Formwork must be adequate to support wet concrete load. We verify shoring post spacing (measure with tape, verify against formwork drawings or industry standards), post bearing (check that base plates are used and posts bear on solid surface not dirt), bracing (lateral bracing between posts prevents buckling), beam sizing (formwork beams supporting deck must be adequately sized), and deck sheathing (plywood thickness adequate, joints supported). If formwork is inadequate, we stop the work until corrected by adding shoring posts, installing bracing, or upgrading beams.
  • We've completed 100+ elevated slab inspections in Fishtown and know common rebar layouts for 3-4 story townhouse construction. Second floor slabs typically use rebar in two layers, concrete stairs use larger bars, concrete columns use vertical bars with ties, and rooftop decks use rebar grids with additional rebar at parapets. We measure actual installation with tape measure checking bar spacing center-to-center at multiple locations, bar size diameter with gauge, cover distances ensuring rebar is the correct distance from surfaces, lap splices measuring overlap length, and chair or bolster spacing verifying rebar is elevated to correct height above formwork.
  • We document each floor separately with detailed photo sets. We take 60-100 photos per inspection showing formwork before rebar, rebar installation with overall grid pattern and spacing measurements with tape visible, lap splices, edge conditions, embedded items like anchor bolts, and any deficiencies found and corrected. Photos are organized by floor in our reports. When L&I reviews at project completion, they see clear progression with no gaps.
How StrucTech Handles Concrete & Rebar Inspection
Common Questions About Concrete & Rebar Inspection
How long does concrete and rebar inspection take in Fishtown?
1.5-3 hours per inspection depending on element complexity. Elevated slab equals 2-2.5 hours including formwork check and rebar inspection. Concrete columns equal 1.5-2 hours. Concrete walls equal 2-3 hours. Concrete stairs equal 1.5-2 hours. For a 3-story Fishtown townhouse with 2-3 concrete pours total, that's 3-6 hours total on-site time spread over 4-8 months. Each inspection delivers report same-day within 6-8 hours.
Can you inspect formwork one day and rebar different day?
Yes, and we recommend this for complex slabs. Typical sequence has contractor build formwork and shoring on Day 1, we inspect formwork before rebar is placed taking 45-60 minutes, if formwork is adequate contractor proceeds with rebar installation on Days 2-3, then we inspect rebar on Day 4 at 30-45 minutes before concrete pour. Separating inspections by 1-3 days gives contractor time to correct formwork issues before rebar work begins. Additional cost for two site visits instead of one, but worth it for large or complex slabs.
What's the difference between this and mat slab inspection?
Mat slab inspection is specifically for ground-level foundation slab as a one-time inspection before building construction begins. Concrete and rebar inspection is for all other concrete elements including elevated slabs (second floor, third floor, roof), concrete columns, concrete walls, concrete stairs, and concrete beams. Key differences are formwork (elevated slabs require temporary formwork and shoring that must support wet concrete weight at elevation, mat slabs pour directly on ground with no formwork), complexity (elevated slabs have top and bottom rebar layers, mat slabs typically one layer), and frequency (mat slab is one inspection, concrete and rebar is multiple inspections throughout construction).
Do you inspect the concrete pour itself or just rebar before?
We inspect rebar before concrete pour which is what Table 1705.3 requires for periodic inspection. We verify rebar is correct, approve pour, and contractor proceeds. We typically don't observe the actual concrete placement unless architect specifically requested continuous observation (different service level, much higher cost because we're on-site 4-8 hours during entire pour), this is a critical structural element, or contractor has history of problems.
What happens if rebar is wrong and concrete trucks are already on the way?
We stop the pour and contractor must reschedule trucks. If we arrive at 6:30am for 7am scheduled pour and measure rebar spacing finding it's wrong, we notify GC immediately that rebar spacing is non-compliant and we cannot approve the pour. GC has two options: fix it immediately if minor by adding rebar bars between existing bars (takes 2-4 hours, reschedule trucks for later today or tomorrow), or reschedule trucks for next day if major issue like wrong bar size requiring removal and replacement.

Our Simple Step by Step Process

Reliable Structural Engineering & Inspection Services handled start to finish.

DISCOVER WHAT Center City, PA CUSTOMERS HAVE TO SAY ABOUT StrucTech

OUR REVIEWS

REVIEW US

ON GOOGLE

Where We Provide

Concrete & Rebar Inspection

  • Center City, PA

  • Northern Liberties, PA

  • University City, PA

  • Main Line, PA

  • Graduate Hospital & Point Breeze, PA

  • South Philadelphia, PA

  • Center City, PA

  • Old City & Society Hill, PA

  • Manayunk & Roxborough, PA

  • Kensington & Port Richmond, PA

Other Services We Provide

Need something else? Check out the

other services we offer for Structural Engineering & Inspection Services.

What We Can Help You With.

Our Services

Special inspections

Special inspections are when a licensed structural engineer monitors your construction project to verify the work matches approved drawings and meets code requirements. Philadelphia requires this for any project using structural steel beams, concrete slabs, high-strength bolts, or structural welding. The inspector visits your site at critical stages during construction, documents what the contractor built, catches problems before they're covered up, and provides certification to L&I when the work is done. Without this certification, L&I won't issue your Certificate of Occupancy and you can't sell or rent the building. Most Fishtown projects over two stories need special inspections, and your architect lists exactly which inspections are required when they submit your permit application.

Learn More →
Underpinning Inspection

An Underpinning inspection is when a structural engineer monitors excavation work next to existing buildings to make sure neighboring properties don't collapse or settle. Philadelphia requires this whenever you dig deeper than 5 feet within 10 feet of an adjacent structure, which is basically every basement excavation in Fishtown's narrow rowhouse lots. Your contractor digs in small sections, pours concrete to support the neighbor's foundation in each section, then moves to the next section. This process repeats 16-24 times for a typical rowhouse. The engineer must be on-site during excavation and concrete placement for every single section to verify the work protects adjacent buildings. Without this documentation, L&I won't issue your Certificate of Occupancy, and if your neighbor's building settles or collapses, you're liable for all damages.

Learn More →
Foundation Inspections

A Foundation inspection is when a structural engineer assesses your building's foundation to identify problems and estimate repair costs. You need this before buying a property to know what you're getting into, before planning a renovation so your architect knows what they're working with, or when you've discovered problems like cracks in walls, doors sticking, floors sloping, or water coming through the basement. Most Fishtown rowhouses are 100-150 years old with stone or brick foundations from the 1800s-1950s. These foundations were fine when built but often show deterioration now from lime mortar crumbling, stones separating, freeze-thaw damage, or settlement from inadequate footings. The engineer accesses your basement and crawlspace, measures cracks, tests mortar condition, checks for water infiltration, documents settlement, and assesses whether the foundation is structurally adequate. You get an 8-15 page report with photos, detailed findings, and repair recommendations with cost estimates.

Learn More →
Make Safe Permits

Make safe permits are emergency L&I permits required when a building partially collapses, shows imminent collapse signs, or gets red-tagged as unsafe. When L&I red-tags a building under Section 110, you must obtain a make safe permit to perform emergency stabilization work like installing shoring, bracing walls, removing dangerous elements, or partial demolition. This permit requires a Pennsylvania-licensed structural engineer to design the emergency work, provide stamped drawings, supervise the stabilization, and certify completion to L&I. The make safe permit is processed on an emergency basis, typically issued within 24-48 hours rather than the normal 2-4 week permit review. Philadelphia averages 300 building collapses per year, many in Fishtown from adjacent excavation damage, roof overloading, fire damage, or century-old buildings deteriorating. Most make safe permit applications happen between 11pm and 3am when buildings collapse during construction, storms, or snow loading events.

Learn More →
Emergency Structural Engineering

Emergency structural engineering is the immediate response when your contractor discovers structural failure during renovation, a load-bearing element fails unexpectedly, or you need same-day structural assessment to keep your project moving. This is when you call us directly because your contractor removed what they thought was a non-load-bearing wall and the second floor sagged 2 inches, opened a wall and found severe termite damage, discovered the existing beam is undersized for the addition you're building, or noticed floor joists rotting where they meet the foundation. In Fishtown's 1800s-1950s rowhouses, contractors frequently discover hidden structural problems during demolition because previous homeowners covered problems with drywall rather than fixing them. The engineer responds within 2-4 hours, assesses damage on-site, designs temporary stabilization for the same day so your contractor can continue working tomorrow, and provides permanent repair drawings within 3-7 days so your project stays on schedule.

Learn More →
Slab Inspection

Mat slab inspection is the code-required inspection by a structural engineer before your contractor pours the foundation slab for new construction or basement excavation projects. Philadelphia Building Code Table 1705.3 requires special inspection of concrete reinforcement placement for most projects, with limited exceptions for simple 1-2 story buildings. Most Fishtown new construction like 3-4 story townhouses and Front Street mixed-use buildings require mat slab inspection. Your contractor excavates to foundation depth, installs vapor barrier and compacted stone base, places reinforcing steel in a rebar grid, and calls the engineer for inspection. The engineer arrives before concrete trucks (typically 6:30am for 7am pour), inspects rebar size, spacing, and cover distances, verifies excavation depth and preparation, approves or identifies corrections, and documents with photos. The contractor proceeds with concrete pour only after engineer approval, and the engineer submits a report to L&I for the permit file.

Learn More →
Concrete & Rebar Inspection

Concrete and rebar inspection is the special inspection required by Philadelphia Building Code Table 1705.3 for elevated slabs, concrete columns, concrete walls, beams, and any structural concrete element beyond simple ground-level foundations. Most Fishtown new construction projects require multiple concrete inspections throughout construction as each floor or structural element is formed and poured. This is different from mat slab inspection which is a one-time inspection before foundation pour. Concrete and rebar inspection happens repeatedly during construction as each floor slab, column, or wall is built. Your contractor builds formwork (temporary wooden forms that hold wet concrete), installs reinforcing steel per structural drawings, calls the engineer for inspection before pouring, and the engineer approves so concrete can be placed. This repeats for each floor slab, each column, and each wall that contains structural concrete, typically requiring 3-8 inspections for a 3-story Fishtown townhouse or 12-24+ inspections for larger buildings.

Learn More →
Structural Steel Inspection

Structural steel inspection is the special inspection required by Philadelphia Building Code Table 1705.2 when your project uses steel beams, columns, or structural frames. Most Fishtown renovation projects remove load-bearing walls to create open floor plans by installing steel I-beams to support the second floor. Most Front Street new construction uses structural steel frames with steel beams and columns supporting concrete slabs in 4-6 story mixed-use buildings. Table 1705.2 distinguishes between continuous inspection where the engineer is on-site during the entire operation (required for welded moment connections and high-strength bolted connections) and periodic inspection with scheduled visits (allowed for standard bolted connections and simple welds). Your contractor orders steel from a fabricator, steel is delivered to site, a crane lifts beams into place, connections are bolted or welded, and the engineer inspects at multiple stages. Typical steel projects require 2-4 inspections for small residential beam installations to 12-24+ inspections for large multi-story steel frame buildings.

Learn More →
Facade Inspection (5-Year)

Facade inspection is the code-required inspection every 5 years for buildings over 3 stories or 40 feet tall per Philadelphia Code Chapter 14-1600. This applies to many Fishtown buildings including converted mills that are 4-6 stories, Front Street mixed-use developments that are 4-8 stories, and some taller rowhouses with pilot-house construction pushing height over 40 feet. A Pennsylvania-licensed Professional Engineer or Registered Architect must inspect the entire building exterior including walls, parapets, cornices, balconies, fire escapes, signs, and awnings looking for deterioration, loose elements, cracks, spalling where concrete or brick breaks off, and any conditions that could cause falling debris. The inspection requires close-up access using aerial lift, scaffolding, or rope access for tall buildings, photo documentation of all defects, and a stamped report submitted to L&I certifying the building is safe or identifying required repairs. Buildings overdue for inspection receive L&I violations with accumulating fines until inspection is complete.

Learn More →
Excavation Shoring Inspection

Excavation shoring inspection is the code-required monitoring by a structural engineer when your contractor digs deeper than 5 feet and uses temporary support systems called shoring to prevent cave-ins. OSHA and Philadelphia Building Code require shoring for excavations over 5 feet deep or when excavating near existing structures to prevent soil from collapsing into the excavation, protect workers from being buried alive, and prevent adjacent buildings from settling. Most Fishtown basement excavations that lower basement floors to add ceiling height or dig new basements under existing buildings require shoring because you're digging 8-12 feet deep and working within inches of adjacent rowhouse foundations. Typical shoring systems are steel sheet piling with interlocking steel sheets driven into ground, soldier piles and lagging with vertical steel beams and horizontal wood planks, or trench boxes as steel cages protecting workers inside excavation. Your contractor installs shoring, the engineer inspects before excavation proceeds, the engineer monitors during excavation, and the engineer certifies shoring performed adequately.

Learn More →
Structural Load Analysis

Structural load analysis is the engineering calculation required when you're adding loads to an existing building or when your architect needs to verify existing structure can support proposed changes. Most Fishtown renovation projects involve structural modifications like removing walls between living room and kitchen to create open floor plan requiring beam to carry second floor load, adding third-floor addition or pilot house where existing structure must support additional story, converting rowhouse to multi-unit rental with heavier occupancy loads, or building rooftop deck where existing roof structure designed for snow only not people and furniture and planters. The engineer calculates existing structural capacity, calculates new loads being added, determines if existing structure is adequate, and designs strengthening if needed with new beams, columns, or foundation upgrades. Deliverables are stamped structural drawings showing required modifications and calculations for L&I permit review. This service is separate from inspection services which verify contractor builds what's on the drawings.

Learn More →
Building Structural Assessment

Building structural assessment is the comprehensive evaluation of your entire building's structural system before major renovations, after discovering problems, for property purchase due diligence, or when converting building use. Most Fishtown building assessments happen when developers buy older rowhouses sight-unseen at auction needing to know actual repair costs before committing capital, architects discover hidden damage during design phase like opened walls and found termite damage or rotted framing or previous unpermitted modifications, or property owners plan gut renovations wanting to know what structural surprises await before setting budgets. The engineer inspects foundation to roof including basement walls and floor framing and load-bearing walls and roof structure, identifies all structural deficiencies, categorizes by severity, and provides repair recommendations with cost estimates. This is different from foundation inspection which focuses only on foundation or pre-purchase home inspection which is general not structural-specific. Building structural assessment is engineering-level detailed inspection with stamped report typically 30-80 pages.

Learn More →

Not sure what you need?

Call us at +1 267-310-1172 and we'll help you figure it out.

Ready to Move Forward?

If you need Concrete & Rebar Inspection

or unsure and have questions let's talk.

We'll answer your questions, provide a clear estimate, and schedule a time that works for you.

Unable to find form